Fecamp Windmill Park Met Mast Tow-out and Installation

In year 2014-2015 Udeco seconded personnel to MT Hojgaard in Copenhagen for engineering management of the tow-out and installation part of the Fecamp Wind Park Met Mast Project offshore Normandy, France.

Back

In year 2014-2015 Udeco seconde dpersonnel to MT Hojgaard in Copenhagen for engineering management of the tow-out and installation part of the Fecamp Wind Park Met Mast Project offshore Normandy, France.

The work also included preparation of installation procedures, anchor system definition / design, and assistance in the hire of anchor systems and anchor handling vessel including ROV for the installation operation. The 4000t ballasted GBS concrete structure including met mast was and successfully installed in February 2015.